Retrospective
- Person
- Issue: One liner
- What I did to help create this situation: one liner
- Proposed solution: one liner
- Issue: One liner
- What I did to help create this situation: one liner
- Proposed solution: one liner
- Issue: One liner
- Person
- Issue: One liner
- What I did to help create this situation: one liner
- Proposed solution: one liner
- Issue: One liner
- What I did to help create this situation: one liner
- Proposed solution: one liner
- Issue: One liner
Example: Mobile App Feature Launch Delay
Context: You're at a fintech startup. The team committed to launching in-app budgeting tools by Q1 end. It's now mid-Q1, and the feature won't ship on time due to expanding requirements and technical issues.
Using the Template:
- Sarah (Product Manager)
- Issue: Budgeting feature will miss Q1 launch by 3 weeks due to 40% scope increase
- What I did to help create this situation: Added 4 new requirements after dev started without adjusting timeline
- Proposed solution: Ship MVP with core tracking only; remaining features in Q2 update
- Issue: Engineers context-switching between budgeting feature and urgent bug fixes -
- What I did to help create this situation: Didn't establish bug triage process; treated all bugs as P0s
- Proposed solution: Dedicate 2 engineers to budgeting until launch; rotate 1 engineer for P0 bugs only
- Issue: Budgeting feature will miss Q1 launch by 3 weeks due to 40% scope increase
- Alex (Senior Engineer)
- Issue: Backend can't handle concurrent budget calculations for >1000 users
- What I did to help create this situation: Didn't load test early; assumed our auth service architecture would work
- Proposed solution: Implement queue system this week; scale horizontally if needed by Friday
- Issue: Frontend-backend contract changes breaking mobile app weekly
- What I did to help create this situation: Skipped API versioning to "move faster"; made breaking changes directly
- Proposed solution: Freeze API changes today; implement versioning before next sprint
- Issue: Backend can't handle concurrent budget calculations for >1000 users
This format shows how different roles own different aspects of the same problem, with no finger-pointing and clear next steps.